Program Evaluation Review Technique (PERT) Chart Explained

Carol M. Kopp edits features on a wide range of subjects for Investopedia, including investing, personal finance, retirement planning, taxes, business management, and career development.

Updated June 19, 2024 Fact checked by Fact checked by Suzanne Kvilhaug

Suzanne is a content marketer, writer, and fact-checker. She holds a Bachelor of Science in Finance degree from Bridgewater State University and helps develop content strategies for financial brands.

PERT Chart

What Is a Program Evaluation Review Technique (PERT) Chart?

A program evaluation review technique (PERT) chart is a graphical representation of a project's timeline that displays all of the individual tasks necessary to complete the project. Put simply, a PERT chart is a project management tool that allows users to map out a project's timeline and itemize individual tasks. This means that the PERT chart allows users to communicate project instructions and set schedules and timelines for projects among other things.

Key Takeaways

How Program Evaluation Review Technique (PERT) Charts Work

A PERT chart uses circles or rectangles, called nodes, to represent project events or milestones. A chart can be made using different types of software. This includes specialized computer software designed to create PERT charts or even a simple program like Microsoft Excel.

The nodes on the PERT chart are linked by vectors or lines that represent various tasks. Dependent tasks are items that must be performed in a specific manner. For example, if an arrow is drawn from Task No. 1 to Task No. 2 on a PERT chart, Task No. 1 must be completed before work on Task No. 2 begins.

Items at the same stage of production but on different task lines within a project are referred to as parallel tasks. They're independent of each other and occur at the same time.

A well-constructed PERT chart looks like this:

Image

A project manager creates a PERT chart in order to analyze all of a project's tasks while estimating the amount of time required to complete each one. Using this information, the project manager can estimate the minimum amount of time required to complete the entire project.

This information also helps the manager develop a project budget and determine the resources needed to accomplish the project.

A PERT chart may make it easier to see and track a project's critical path. The critical path is the minimum time it will take to complete a project, based on the longest path from start to finish.

How to Interpret a PERT Chart

A PERT chart is a visual representation of a series of events that must occur within the scope of a project’s lifetime. The direction of the arrows indicates the flow and sequence of events required.

Dotted activity lines represent dummy activities. These are items that are located on another PERT path. Numbers and time allotments are assigned and shown inside each vector.

These charts have their distinct definitions and terms, the most important of which is anticipating how long it will take to finalize a project:

A PERT chart is similar to a critical path analysis, which is another method that project managers use to chart tasks in a project. The main difference between the two is that a PERT chart uses various time frames and probability terms when estimating each project stage.

Advantages and Disadvantages of PERT Charts

As a project management tool, PERT charts have distinct advantages and disadvantages.

Advantages

A PERT chart allows a manager to evaluate the time and resources necessary to complete a project. It also allows the manager to track required assets during any stage of production in the course of the project.

PERT analysis incorporates data and information supplied by a number of departments. This combining of information encourages department responsibility and identifies all responsible parties across the organization.

It also improves communication during the project and it allows an organization to commit to projects that are relevant to its strategic positioning.

PERT charts are useful input for what-if analyses. Understanding the possibilities concerning the flow of project resources and milestones allows management to achieve the most efficient and useful project path.

Disadvantages

The information that goes into a PERT chart can be highly subjective. They may include unreliable data or unreasonable estimates for cost or time.

PERT charts are deadline-focused and might not fully communicate the financial positioning of a project.

Creating a PERT chart is labor-intensive, and maintaining and updating the information requires additional time and resources. Continual review of the information provided, as well as the prospective positioning of the project, is required for a PERT chart to be of value.

PERT Chart vs. Gantt Chart

The Gantt chart goes back even further than the PERT chart. American mechanical engineer Henry Gantt designed it sometime in the second decade of the 20th century and it remains the most widely used project management chart.

Like the PERT chart, the Gantt chart is a graphical depiction of a project timeline. Presented as a horizontal bar chart, it records the start and completion dates of each element of a project and indicates their interdependencies. The two charts are used in similar ways:

Early versions of the Gantt chart did not show dependencies. That is, it didn't indicate where a delay in the completion of one task could hold up the start of another task, potentially throwing a whole project off schedule. Later versions of Gantt corrected this.

Although it may be difficult to interpret, the PERT chart is often preferred to the Gantt chart a project management tool because it identifies task dependencies. In some cases though, project managers may use a PERT chart as part of the planning stage of a project and a Gantt chart to monitor its execution.

Example of PERT Chart

PERT charts were first created by the U.S. Navy's Special Projects Office in the 1950s to guide the Polaris Fleet Ballistic Missile project. Using the PERT model, Navy project managers were able to:

The success of this initial use of PERT charts has caused them to be used ever since in many industries.

What Are the Main Components of a PERT Chart?

A PERT chart displays all of the key deliverables necessary to complete a project. It indicates the amount of time and resources needed to perform each task and the person or department responsible for each. The key deliverables or tasks are displayed with arrows that indicate the order in which each must be completed, and the dependencies among them.

How Can I Create a PERT Chart?

Microsoft Excel can be used to create a PERT chart. Custom software with ready-made templates, such as Lucidchart, also are available.

Why Would I Use a PERT Chart Instead of a Gantt Chart?

A PERT chart requires a project manager to think through three possible timelines: Optimistic time is the shortest possible route to completion. Pessimistic time is the longest it might take if everything goes wrong. The most likely time is a reasonable estimate of the best-case scenario.

From the outset, the project manager has defined the ideal outcome of a project but also identified the possible barriers to achieving that outcome.

The Bottom Line

Project management can be a very daunting and challenging task. But there are tools that managers can use to help make the process a little smoother. The PERT chart can help project managers visually map out the project's timeline by highlighting all the tasks involved. It also helps managers by laying out project instructions and the timeline needed to complete each individual task. Charts can be created using specialized computer software or even Microsoft Excel.

Article Sources
  1. Special Projects Office Bureau of Naval Weapons Department of the Navy. "PERT Summary Report Phase 1."
  2. Indeed. "How To Create PERT Charts in Excel (With Tips and FAQ)."
  3. Malcolm, D.G., et al. "Application of a Technique for Research and Development Program Evaluation," Operations Research, vol. 7, no. 5, 1959, pp. 646-669.
  4. Gantt Charts. "Henry Gantt's Legacy to Management is the Gantt Chart."
  5. Smart Sheet. "PERT Chart vs. Gantt Chart."
Related Terms

IRS Schedule K-1 is a document used to describe the incomes, losses, and dividends of a business's partners or an S corporation's shareholders.

An inside sale happens when customers are sold products and services through the phone or online rather than at the vendor's physical location.

Bonus depreciation is a tax break that allows businesses to immediately deduct a large percentage of the purchase price of eligible assets.

A media kit is a package of information a company assembles to provide reporters or other interested parties with basic information about itself.

A multiple employer plan (MEP) is a retirement savings plan that covers two or more employers. It enables small companies to offer big-company benefits.

A multiple employer welfare arrangement (MEWA) is a vehicle for marketing health and welfare benefits to employers for their employees.

Related Articles

A man and a woman in an office laugh together over something they have seen on a laptop screen.

Best LLC Services for September 2024

Health Insurance for Small Business Owners

Best Health Insurance Companies for Small Businesses for September 2024

Best Payroll Software

The Best Payroll Software for September 2024

SBA Lenders

Best SBA Lenders for September 2024

Female small business owner turning open sign in her store

How to Qualify for an SBA Loan in 2024

A couple sits on a couch holding documents and looking at a laptop; they're opening a business bank account.

Best Small Business Bank Accounts for September 2024 Partner Links Investopedia is part of the Dotdash Meredith publishing family.

We Care About Your Privacy

We and our 100 partners store and/or access information on a device, such as unique IDs in cookies to process personal data. You may accept or manage your choices by clicking below, including your right to object where legitimate interest is used, or at any time in the privacy policy page. These choices will be signaled to our partners and will not affect browsing data.

We and our partners process data to provide:

Store and/or access information on a device. Use limited data to select advertising. Create profiles for personalised advertising. Use profiles to select personalised advertising. Create profiles to personalise content. Use profiles to select personalised content. Measure advertising performance. Measure content performance. Understand audiences through statistics or combinations of data from different sources. Develop and improve services. Use limited data to select content. List of Partners (vendors)